Since the project began, traffic has been detoured through MD 185 to MD 192 to Stoneybrook Drive and Beach Drive. The roadway is now scheduled to be reopened to traffic on April 1, although the contractor will be performing final paving, striping and landscaping in early July.
A new pedestrian bridge constructed as part of the project was opened on Sept. 1.
To meet the new accelerated construction schedule, additional crews are being added. Construction will take place Monday through Friday between 7 a.m. and 5 p.m. and may include Saturday work. Residents living near the site may hear construction-related noise during these hours.
A 2020 bridge inspection revealed that the bridge’s steel arches are in poor condition. The south parapet has been removed above two arches and temporary concrete traffic barriers were put in place. The project, which will allow the bridge to be restored to full capacity, is being partially funded with Federal funds.
The project includes replacement of the two-lane bridge, relocating Rock Creek Trail to a separate alignment, constructing a pedestrian bridge crossing of Silver Creek and removing the right turn lane of Kensington Parkway at Beach Drive. The project also will plant trees, incorporate landscaping and implement erosion control measures.
For questions about construction, contact the MCDOT on-site Construction Representative Glenn Hane at Glenn.Hane@montgomerycountymd.gov or MCDOT Field Supervisor Bill Sittinger at Bill.Sittinger@montgomerycountymd.gov.